| 1. |
Analyzing the competition and integration between the eastern railway and highway systems.
|
| 2. |
Proposing a feasible plan of railway high speed for establishing a rapid, safe, and green public transportation system.
|
| 3. |
The ultimate objectives of this project are to balance the regional development and promote the economical
bloom of eastern Taiwan.
|
| D. Estimated cost & Planning Period: |
|
The total construction cost estimated to be N.T.$13.50 million. The project schedule is from April 2003 to
November. 2003.
|
| E. Benefits: |
| 1. |
The analysis of the competition and integration between railway and highway systems in eastern region.
|
| 2. |
The feasible plan for railway high speed, including as follows: |
|
(1) Determination of the goal of high speed.
(2) Analysis of current railway conditions.
(3) Examination of speed limited factors.
(4) Study of feasible plans.
(5) Analysis of environmental impact.
|
| 3. |
Cost / benefits analysis of the proposed feasible plan.(including alternative plan) |
| 4. |
Financial analysis and financing plan. |
| 5. |
Feasibility study of private sector participation.(including BOT) |
| F. Status of implementation: |
|
Completed the review of mid-term report. |