Hualien-Taitung Line Electrification Project
Hualien-Taitung Line Electrification Project (2016-07-18 updated)

Summary:
The Executive Yuan approved the Hualien-Taitung Line Electrification Project on March 13, 2008 for the purpose of upgrading railway services in eastern Taiwan and thus further promoting the tourism industry there. Not only completing a modern railway network round the island, it is also meant to accommodate fast-growing demand for rapid transport in this part of the island. Spanning about 166.1 kilometers from Hualien Station to Zhiben Station in Taitung, the project will electrify the entire route, lay double tracks in the bottleneck sections, and build four double-track tunnels and three bridges. Duration to the project is from 2008 to 2018. This Project was opened for operation on June 28, 2014. In 2016 subsequent works are under way on new Ziqiang Tunnel.

Performance:
The viaduct station of Shoufeng and the section from Shoufeng to Nanping for the project was opened for operation on Aug 26 and Oct 20, 2015 separately. The new Ziqiang Tunnel has been drilled through on Oct. 20, 2015.
Hualian-Taitung Electrification Project
link Link: The Reconstruction Project for Taitung Station has Successfully Contracted Out (Open New Window)
link Link: The Minister of MOTC Inspects the New Ziqiang Tunnel of Hualien-Taitung Electrification Project (Open New Window)
link Link: President Ma Inspects the New Ziqiang Tunnel Engineering of Hualien-Taitung Electrification Project (Open New Window)
link Link: MOTC Minister Yeh Inspects Engineering of Yue-Mei Elevated Tracks Railway Construction (Open New Window)
link Link: New Shan-Li Tunnel Main West Line is Completed and Open to Traffic On August 29, 2013 (Open New Window)
link Link: Civil Work Engineering for Entire Hualien-Taitung Line Electrification Project Line is Completed (Open New Window)
link Link: MOTC Minister Yeh Inspected the Engineering Site of Hualien-Taitung Line Electrification Project (Open New Window)
link Link: Track Switch Over Engineering on Fengping River Bridge is Successfully Completed (Open New Window)
link Link: President Performed On-site Inspection of Hualien-Taitung Line Electrification Project (Open New Window)
link Link: Hualien-Taitung Line Electrification Project’s Guangfu Substation (Open New Window)
link Link: On June 28, 2014, Hualien-Taitung Railway Line Celebrates the Coming of “Electricity” (Open New Window)
link Link: Xinziqiang Tunnel Opened on October 20 (2015) (Open New Window)
link Link: Drilling on Both Ends of Hualien-Taitung Line Xinziqiang Tunnel Now Complete (Open New Window)
link Link: Feasibility Study on Converting Hualien–Taitung Line to Double Track (Open New Window)
link Link: Completion of New Tzechiang Tunnel on Hualien - Taitung Line (Open New Window)
link Link: New Tzechiang Tunnel Came into Use on September 25th, 2017. (Open New Window)

Back


  Copyright © 2008 Railway Reconstruction Bureau, Ministry of Transportation and Communications. All rights reserved.
20F., No.7, Sec. 2, Xianmin Blvd., Banqiao Dist., New Taipei City 220, Taiwan (R.O.C.)
Tel:+886-2-8969-1900 Fax:+886-2-8969-1823
Privacy PolicyInformation Security PolicyGovernment Website Open Information Announcement
A+ Accessibility Level gov